Helsinki's district-heating network had depended on burning coal. Helen, the city's energy company, had already stopped coal production at the Salmisaari A heating plant and had closed its Hanasaari plant in 2023. Salmisaari B was a combined heat and power plant, so retiring it meant planning for changes in two outputs. Helen's August 2023 site plan put the shutdown of B on April 1, 2025 and set out a separate set of projects to replace heat production. [1][2]
The plan combined two 50 MW electric boilers, an industrial air-to-water heat pump, a conversion from coal to pellets at the A heating plant and work on existing heat storage. Helen described the pellet unit as intended for periods of high winter demand. In the plan, the heat pump could also provide district cooling during summer. The components were designed to meet different needs in the wider heat network. [1]
On April 1, 2025, Yle reported that the Salmisaari coal-fired power and heating plant had closed. Helen identified it as the end of its own coal use. The report also explained that Finland still maintained coal reserves and that other operators could use small amounts. The event was the end of coal at Helen and a major step in national use, with different boundaries for each claim. [2][3]
Helen's 2025 financial statements say that the two electric boilers, the air-to-water heat pump and the converted pellet boiler entered commercial operation during the year. The company reported that its annual emissions roughly halved compared with 2024. That was Helen's company-level result. The year’s consolidated heat sales also fell, to 5,425 GWh from 5,981 GWh, which is one reason not to infer an exact efficiency improvement from the emissions percentage alone. [3]
A coal-fired plant had bundled fuel storage, combustion and combined heat and electricity production at one site. The replacement heat system distributed those functions. Electric boilers can supply heat directly from electricity. A heat pump draws part of its heat from an available source, but output depends on operating conditions. Storage helps move the timing of some heat production, and pellet-fired capacity can contribute during higher demand. The original site plan explicitly designed for more than one source. [1][2]
Replacing a plant within a network also allows planners to distinguish nameplate capacity from available heat during a cold spell. The electric boilers' combined 100 MW rating is one component of the plan, not a measure of what the whole city can draw from the site in every hour. Electrical connection limits, demand, temperature, fuel and storage conditions all affect dispatch. The plan and commissioning reports describe capacity decisions, leaving operational comparisons for measured data. [1][3]
Analysis & application
Start a similar retirement plan with a heat-demand profile rather than an annual fuel total. Calculate which equipment will meet ordinary loads, which equipment can respond during a cold snap, and how the electricity network and heat store affect that ability. Set a retirement milestone only after deciding how the operator will verify replacement capacity, coordination and recovery from a failure on a winter day. [1][2]
Track actual heat delivered by source, peak availability, bought electricity, fuel, emissions and customer prices with the periods and boundaries clearly stated. A year with lower heat sales can make a transition look different from one with an unusually cold winter. Compare like demand conditions before assigning savings to a particular boiler, fuel or operating decision.
Helen said that lower production costs and a reduced need for emissions allowances helped district heating return to profitability in 2025. At the group level, reported operating profit rose while comparable operating profit was lower. Those figures make the results more useful than a single claim that the plant closure improved every financial measure. The case shows what was commissioned and how the operator replaced coal capacity. Measuring performance across later winters will show how well the new mix handles changing demand and electricity prices. [3]
FOLLOW THE EVIDENCE
The sources
- Renewal of the Salmisaari production site Helen · helen.fi ·
- Helsinki’s energy firm says goodbye to coal as it shuts down the Salmisaari power, heating plant Yle News · yle.fi ·
- Helen’s financial statements release 2025 Helen · helen.fi ·