In 2012 the Federal Communications Commission set aside up to US$300 million in one-time support for mobile voice and broadband in areas it identified as unserved. The agency did not ask carriers to compete for spectrum or submit bids based on the number of subscribers they expected. In Auction 901, a single sealed bidding round held on September 27, providers stated how much support they would need per qualifying road mile to serve an eligible geographic area. The road-mile total for that area was defined before bids were submitted. [1] [2]

The agency ranked bids by requested support per mile, with a 25% adjustment for comparing qualifying bids from eligible Tribal entities. For a selected bid, the support calculation used the actual bid per mile multiplied by the qualifying miles. The system did not select multiple bidders for the same area and could skip an otherwise competitive bid if its total exceeded what remained in the fund. [1]

The closing notice identified 33 winning bidders eligible for US$299,998,632 in total support. Their winning areas included up to 83,494.23 qualifying road miles in 795 areas across 31 states and one territory. These are measures of what the auction selected and what the bids covered. The notice did not certify that every road mile was already served, and winning bidders still had to submit a more detailed application before they could receive authorized support. [2]

Telephone and Data Systems, the parent of U.S. Cellular, later reported that U.S. Cellular and certain subsidiaries won in eligible areas in ten states. They were eligible for up to US$40.1 million and had received US$13.4 million by December 31, 2013. That disclosure shows how the amount attached to a winning bid can differ from what an operator has actually received at a given date. It does not describe the deployment results of all 33 winners. [3]

The auction turned a complex proposal into a comparable price for a defined unit of service. A request for less subsidy per mile generally ranked ahead of a request for more, but coverage rules still determined what the public got for the money. Providers committing to 3G had two years from authorization to serve at least 75% of the designated road miles. The corresponding deadline for a 4G commitment was three years. The standards covered service performance as well as the presence of a network. [1] [3]

The FCC required a post-auction description of the project, including its budget, technology, schedule and milestones. It also set out evidence requirements, including drive tests for road coverage, and provided for different consequences for failing to secure authorization and failing to meet performance obligations after authorization. The winning price alone was not enough to establish delivery. [2]

Analysis & application

When designing a reverse auction for infrastructure, first choose an outcome that bidders can price and the buyer can verify. A road mile is useful when the goal includes connectivity along travel routes. It is a poor substitute for the number of households that gain service or the reliability of their connections. A procurement team should map the population and places it aims to reach before choosing which unit governs the ranking. [1] [4]

Keep separate records of the bid, authorization, money paid and coverage accepted. Publish the verification method and test whether the bidding unit rewards providers for serving places with the most pressing gaps. Where costs, routes or coverage maps are uncertain, a low bid should lead to further verification rather than a presumption that the promised service already exists. [1] [2] [3]

Congressional Research Service described a separate Tribal Mobility Fund intended to address additional unmet needs. The national auction remains a case in how a buyer can compare subsidy requests with a common denominator and then verify delivery as a separate step. Its closing notice documents the commitments selected, not the final coverage of the program. [2] [4]

FOLLOW THE EVIDENCE

The sources

  1. Mobility Fund Phase I Auction Scheduled for September 27, 2012: Notice and Filing Requirements and Other Procedures for Auction 901 Federal Register; Federal Communications Commission · regulations.justia.com ·
  2. Mobility Fund Phase I Auction Closes; Winning Bidders Announced for Auction 901 Federal Communications Commission · docs.fcc.gov ·
  3. Telephone and Data Systems Inc. Form 10-K for 2013 Telephone and Data Systems, filed with the U.S. Securities and Exchange Commission · sec.gov ·
  4. Rural Broadband: The Roles of the Rural Utilities Service and the Universal Service Fund Congressional Research Service · everycrsreport.com ·