Feldschlösschen’s Rheinfelden brewery had to coordinate a product through several steps before it could ship. Beer occupies tanks during fermentation and maturation, passes through filtration, may wait in a buffer tank and is finally filled into bottles, cans or kegs. Certain products, such as specialty and alcohol-free beers, need additional equipment. A week with spare filling capacity can still be difficult to schedule if the right beer has not finished in the right tank. [1] [2]
Markus Mickein, Matthes Koch and Knut Haase at the University of Hamburg worked with the brewery to put these dependencies into one planning tool. The system pulled basic product, resource and demand data from the enterprise system and supplemented it with spreadsheets. It checked the inputs before running the optimization and showed the results to planners in a common report. The project paper describes a model covering 13 production resources, eight storage resources and a planning horizon of up to 52 weeks. [1] [2]
The team used the tool for three kinds of decisions: preparing production schedules, deciding when shifts or temporary capacity might be needed and evaluating changes to products or equipment. It made it possible to compare scenarios across the whole system rather than reporting only how one machine or department would be affected. The project authors reported less planning effort and identified ways to reduce operational costs or avoid ineffective investments. Their public accounts do not establish an independently measured percentage saving. [1] [2]
The brewery’s separate 2022 performance report describes rising sales of alcohol-free, craft and specialty beers, illustrating the kind of mix changes the planning team needed to evaluate. The company also described changes in its markets and new business activities. Its sales figures are context for the planning problem, not an outcome that can be assigned to the optimizer. [3]
The project treated time in a tank as capacity in its own right. Making more of a product at one stage can crowd out another product at the next, even when each department’s total labor hours look adequate. Modeling those stages together let planners see which resource became the bottleneck when they changed the mix, shift pattern or equipment. A 52-week horizon made longer-term comparisons possible, but it did not guarantee that demand or equipment availability would follow any one scenario. [1] [2]
The team involved the relevant departments during development. A report could identify when a scenario required capacity beyond a stated limit and show planners which assumption would have to change. A scenario asking for additional capacity was a signal to revisit the plan, not evidence that the extra capacity existed. [2]
Analysis & application
For a similar operation, map the time each product spends at each step and identify which resources can actually substitute for one another. Then compare a base schedule with scenarios for a demand surge, maintenance downtime and a change in product mix. Keep service requirements fixed while testing alternatives, and ask operators to review any scenario that shifts the bottleneck from one team to another. [1] [2]
Keep an explicit list of constraints that cannot be relaxed and ones that may change if management approves more capacity. In the results, distinguish observed operating costs from costs predicted for a scenario. If a purchase is deferred, record why and revisit the decision when real utilization and demand are known. That makes the tool useful for deciding what to buy as well as for scheduling the equipment already installed. [1] [2]
The research team identified handling uncertain demand and adapting the tool to other sites as future work. Those were prospects, not claims of completed rollouts. For a brewery or another factory, the transferable principle is to let people see how a decision at one stage consumes time or space at another before committing to a production plan. [2]
FOLLOW THE EVIDENCE
The sources
- A Decision Support System for Brewery Production Planning at Feldschlösschen INFORMS Journal on Applied Analytics · pubsonline.informs.org ·
- Optimisation Keeps the Beer Flowing The Operational Research Society, Impact; university-hosted author copy · bwl.uni-hamburg.de ·
- Jahreskennzahlen 2022: Unternehmen Feldschlösschen erschliesst neue Geschäftsfelder Feldschlösschen · feldschloesschen.swiss ·