Gateway Terminals India, the APM Terminals operation at Jawaharlal Nehru Port, put an automated truck appointment system live on September 29, 2025. The terminal operator said truckers were to choose an available time slot for entry. Arunjay Kumar Singh, the terminal’s chief executive, and Vimal Kumar Srivastava, the chief commissioner of Customs Mumbai Zone II, took part in the inauguration. The announcement described a prior run-through with stakeholders. The goal was to spread arrivals and make pickups and deliveries easier to plan. [1]

The port had discussed the underlying problem months earlier. At a May 28 meeting, container freight station operators described recurring congestion. Terminal heads reported a concentration of arrivals between 2 p.m. and 10 p.m., with quieter late-night and early-morning periods. APM Terminals already told the meeting it was using appointments and had assigned freight stations to two groups with different time slots. The September date refers to the announced automated launch; it should not erase evidence of the earlier arrangements. [1][2]

At an October 15 meeting, JNPA officials recorded the Gateway Terminals India system as a measure to streamline container evacuation. The operator expected shorter turnaround and better planning. That expectation is distinct from a measured reduction for a defined group of truck visits. The launch statement and October port record do not supply a before-and-after distribution for gate waiting or terminal dwell time. [1][3]

Customs minutes published later recorded the terminal’s October volume as 163,031 gate TEUs, a measure expressed in twenty-foot equivalent units rather than a truck count. The minutes attributed a report of improved import evacuation to the terminal and also recorded other measures, including traffic attendants, surveillance and coordination with freight stations. Those changes occurred alongside appointment arrangements. The figures give scale, but they cannot isolate how much of any improvement came from automation. [4]

An appointment can move visits out of the busiest period if dispatchers have usable alternatives and if the terminal can process the booked work at those times. The visible reservation tells a carrier when to send a truck and tells the terminal when demand is likely to arrive. The May record shows why that coordination mattered: capacity could be underused in one part of the day while traffic queued in another. [1][2]

A gate slot also has to match the rest of the workflow. The carrier needs a ready truck, the necessary identifiers and a container that can be handled. Freight stations raised concerns in May about missing a slot; APM Terminals described a way to handle some trucks if another pickup identifier was available. A rigid slot policy can transfer delays from the gate to freight stations or drivers if exceptions are too difficult to resolve. [2][4]

Analysis & application

Before choosing appointment capacity, measure arrivals by time of day and separate pre-gate queuing from time inside the terminal. Start with the operation that actually limits capacity, such as security checks, yard handling or container availability. Keep a defined route for late arrivals and missed slots. Then follow the share of slots used, how often dispatchers rebook, and the time and costs moved elsewhere in the supply chain. [2][4]

When reporting results, compare similar hours and cargo flows and document equipment, staffing and vessel schedules during each period. Use medians and upper percentiles of waiting time rather than relying on gate throughput alone. Also ask carriers and freight stations whether predictable slots improved their ability to assign a driver to a second job. That distinction helps separate terminal output from predictability for users. [2][3][4]

Customs minutes show that terminal-to-freight-station coordination remained an operating issue after the launch. They describe sharing import pendency information twice daily and arranging timely placement of empty trailers. These are complementary tasks: a reservation schedules arrival, while the readiness of people, vehicles and containers determines whether the reserved move can go ahead. The available public evidence supports the existence of the system and its role in the operating plan. It does not establish a quantified standalone effect on congestion. [3][4]

FOLLOW THE EVIDENCE

The sources

  1. Gateway Terminals India optimises truck handling with new Truck Appointment System APM Terminals · akamai.apmterminals.com ·
  2. Minutes of the Meeting held with CFS’s & Terminal Operators regarding Congestion at Terminal Gates on 28th May 2025 Jawaharlal Nehru Port Authority · jnport.gov.in ·
  3. Minutes of the Port Customers’ Meeting held on 15th October, 2025 Jawaharlal Nehru Port Authority · jnport.gov.in ·
  4. Permanent Trade Facilitation Committee (Export & General), November 2025 minutes Jawaharlal Nehru Custom House · jawaharcustoms.gov.in